Saturday, August 10, 2013
Monday, September 3, 2012
Determination of the Corrosion Levels
A. Find the Corrosion
Levels.
(1) Corrosion found on a
structure when you use the Corrosion Program and Corrosion Prevention 7(CPCP)
Baseline Program will help find the extent of the corrosion.
(2) The second and
subsequent inspections will find how well the CPCP program has been prepared or
if there is a need to make adjustments to the Baseline Program.
(3) A good quality CPCP
is one that controls corrosion to Level 1 or better.
(4) If Level 2 corrosion
is found during the second or subsequent inspection, you must do something to
decrease the future corrosion to Level 1 or better.
(5) If Level 3 corrosion
is found, you must also do something to decrease the future corrosion to Level
1. Also, a plan to find or prevent Level 3 corrosion in the same area on other
airplanes must be added to the CPCP.
(6) All the corrosion
that you can repair in the allowable damage limits, (less than 10 percent of
the part thickness) is Level 1 corrosion.
(7) If all corrosion is
Level 1, the CPCP is correctly prepared.
(8) If you must
reinforce or replace the part because of corrosion, the corrosion is Level 2.
(9) If the part is not
airworthy because of the corrosion, you must do an analysis to find out if the corrosion
is Level 3.
(10) The chart found in
this section will help find the level of the corrosion.
(11) The probability that the same problem will
occur on another airplane is dependent on several factors such as: past
maintenance history, operating environment, years in service, inspectability of
the corroded area and the cause of the problemActions Follow Corrosion
A. If corrosion is
found, find the corrosion level, then do the necessary steps for a specific
inspection.
B. If Level 1 corrosion
is found during the first CPCP inspection.
(1) Repair the
structure. Contact Cessna for an
approved repair procedure.
(2) Continue with the
Baseline Program.
(a) Optional: Document
the results of the inspection for use in validating program compliance.
C. If Level 2 corrosion
is found during the first CPCP inspection.
(1) Repair the
structure. Contact Cessna for an
approved repair procedure.
(2) Report the details
of the corrosion you see to Cessna Aircraft Company and the DGCA.
(3) Continue to use the
Baseline Program but check the corroded area carefully when you do a subsequent
CPCP inspection.
(4) It is recommended
that you record the results of the inspection to show compliance with the program.
D. If Level 3 corrosion
is found during the first CPCP inspection.
(1) Immediately contact
Cessna Aircraft Company and the DGCA of the
corrosion you found.
(2) Give sufficient
information to make sure that the condition is a possible urgent airworthiness concern
for your fleet. Get assistance from Cessna Support
to develop a plan of action.
(3) Apply the corrosion
program inspection, which includes the repair of the structure. Contact Cessna
Aircraft Company for an approved repair procedure.
(4) Do a report that has
the information of the findings. Refer to Corrosion Prevention And Control Program
Reporting System - Description And Operation.
(5) Continue with the
Baseline Program and other steps of procedure required by the DGCA. Examine this area carefully during future inspections.
E. If no corrosion is found
during the second or subsequent CPCP inspection:
(1) Continue with the
current Corrosion Prevention and Control Program. No adjustment of the current
program is required.
(2) It is recommended
that you record the results of the inspection for a possible increase of the corrosion
inspection interval.
.
Corrosion Found
If Level 1 corrosion
is found on the second or subsequent CPCP inspection:
(1) Do the corrosion
program inspection, which includes the repair of the structure. Contact Cessna Aircraft
Company for an approved repair procedure.
(2) Continue with the
Baseline Program.
(3) No adjustment of the
existing program is required.
(4) It is recommended
that you record the corrosion inspection number and the results of the inspection
to show that the program was complied with.
If Level 2 corrosion
is found on the second or subsequent CPCP inspection:
(1) Repair the
structure. Contact Cessna Aircraft Company for an approved repair procedure.
(2) Do a report that
shows the information about the corrosion and send it to Cessna Aircraft Company
and the FAA (or applicable regulatory authority).
(3) If corrosion damage
required the removal of material just beyond the allowable limits (within 10 percent),
complete a check of the other airplanes in the fleet before you change your
aircraft's maintenance program.
(a) If the corrosion is
typical of Level 2, use the fleet data to find what changes are required to control
corrosion to Level 1 or better.
(b) If fleet damage is
typically Level 1, examine the corroded area during subsequent inspections on
all affected airplanes.
(c) Make changes to your
aircraft's maintenance program if the typical corrosion becomes Level 2.
(4) Further evaluation
by Cessna Aircraft Company is recommended for Level 2 corrosion findings that
are well beyond the allowable limits and there is an airworthiness concern in
which prompt action is required.
NOTE: The airworthiness concern is because of the possibility to have similar but
more severe corrosion on any other airplane in the operator's fleet prior to
the next scheduled inspection of that area.
(5) Find the action required to control the
corrosion to a Level 1 or better, between future successive inspections. These
can include the items that follow:
(a) A structural
modification, such as additional drainage.
(b) Improvements to the
corrosion prevention and control inspections, such as more care and attention
to corrosion removal, reapplication of protective finish, drainage path
clearance.
(c) Decrease the
inspection interval for additional airplanes that go into the program.
(6) Send a plan of
corrective action to the FAA (or applicable regulatory authority) for approval
and to Cessna Aircraft Company as needed.
(7) Use the approved plan of action.
H. If Level 3 corrosion
is found on the second or subsequent CPCP inspection:
(1) Contact Cessna
Aircraft Company and the FAA (or applicable regulatory authority) about the corrosion
that was found.
(2) Send a plan to
examine the same area on other affected airplanes in the operator's fleet.
(3) Apply the corrosion
program inspection, which includes the repair of the structure. Contact Cessna
Aircraft Company for an approved repair procedure.
I. Find the action
needed to control the corrosion finding to Level 1 or better, between future
successive inspections. These can include any or all of the following:
(1) A structural
modification, such as additional drainage.
(2) Improvements to the
corrosion prevention and control inspections, such as more care and attention
to corrosion removal, reapplication of protective finish, drainage path
clearance.
(3) A decrease in the
inspection interval for additional airplanes entering the program.
J. Send a plan of
corrective action to the FAA (or applicable regulator authority) for approval
and Cessna Aircraft Company as needed.
K. Use the approved plan
of action.
L. It is recommended that you give the details of
the findings to Cessna Aircraft CompanyFactors Influencing Corrosion Occurrences
If you find Level 2
or Level 3 corrosion, when you think about how to change your CPCP, think about
the list that follows.
(1) Is there a presence
of LPS-3 Heavy-Duty Rust Inhibitor?
(2) Is there a presence
or condition of protective finish?
(3) What was the length
of time since the last inspection and/or application of corrosion inhibiting compound?
(4) Was there inadequate
clean-up/removal of corrosion prior to application of corrosion inhibiting compound,
during previous maintenance of the area?
(5) Are the moisture
drains blocked or is there inadequate drainage?
(6) What was the
environment, the time of exposure to the environment and the use of the
airplane?
(7) Was there a
variation in past maintenance history and or use of the airplanes in the
operator's fleet?
(8) Were there
variations in the production build standard in the operator's fleet?
CPCP Baseline Program Implementation
The Baseline Program is divided into specific
inspection areas and zone locations. The inspection areas and zone locations
apply to all airplanes.
Reporting
System
A. CPCP Reporting System
(1) The CPCP includes a system to report to Cessna
data that will show that the Baseline Program is sufficient and, if necessary, make
changes.
(2) At the start of the second Corrosion Program
Inspection of each area, report all Level 2 and Level 3 Corrosion results that
are listed in the Baseline Program to Cessna.
Send the Control Prevention and Control Program
Damage Reporting Form to: Cessna.
Periodic
Review
A. Use the Service Difficulty Reporting System to
report all Level 2 and Level 3 Corrosion results to the FAA and to Cessna. All
corrosion reports received by Cessna will be reviewed to determine if the
Baseline Program is adequate.
Corrosion Related Airworthiness Directives
A. Safety-related corrosion conditions transmitted
by a Service Bulletin can be mandated by an Airworthiness Directive (AD).
Appendix A - Development Of The Baseline
Program
A. The CPCP Baseline Program
(1) The function of the CPCP is to give the minimum procedures necessary to
prevent and control corrosion so that continued airworthiness is not at risk.
The PSE's are areas where the CPCP applies.
(2) The CPCP Baseline Program consists of a
Corrosion Program Inspection (CPI) and an inspection time. Each inspection is
to be done in an airplane zone.
CPCP – Base Line
Introduction: Corrosion can cause damage to the airplane's structural integrity and if it is
not controlled, the airframe will carry less load than what is necessary for
continued airworthiness.
(1) A CPCP is
a system to control the corrosion in the airplane's primary structure. It is
not the function of the CPCP to stop all of the corrosion conditions, but to
control the corrosion to a level that the airplane's continued airworthiness is
not put in risk.
CPCP Function
A. The function of this document is to give the
minimum procedures necessary to control the corrosion so that the continued
airworthiness is not put in risk. The CPCP consists of a Corrosion Program Inspection
number, the area where the inspection will be done, specified corrosion levels
and the compliance time. The CPCP also includes procedures to let Cessna and the regulatory authorities know of the
findings and the data associated with Level 2 and Level 3 corrosion.
This includes the actions that were done to
decrease possible corrosion in the future to Level 1.
Baseline
Program
A. The Baseline Program is part of the CPCP. It is
divided into Basic Task and Inspection Interval. In this manual the Basic Tasks
are referred to as the Corrosion Program Inspection. This program is to be used
on all airplanes without an approved CPCP. Those who currently have a CPCP that
does not control corrosion to Level 1 or better must make adjustments to the
areas given in the Baseline Program.
B. Typical Airplane Zone Corrosion Program
Inspection Procedures.
(1) Remove all the equipment and airplane interior
(for example the insulation, covers and, upholstery) as necessary to do the
corrosion inspection.
(2) Clean the areas given in the corrosion
inspection before you inspect them.
(3) Do a visual inspection of all of the Principal
Structural Elements (PSEs) and other structure given in the corrosion
inspection for corrosion, cracking and deformation.
(a) Carefully examine the areas that show that
corrosion has occurred before.
NOTE: Areas that need a careful inspection are given in
the corrosion inspection.
(b) Nondestructive testing inspections or visual
inspections can be needed after some disassembly if the inspection shows a
bulge in the skin, corrosion under the splices or corrosion under fittings.
Hidden corrosion will almost always be worse when fully exposed.
(4) Remove all of the corrosion, examine the damage
and repair or replace the damaged structure.
(a) Apply a protective finish where it is required.
(b) Clean or replace the ferrous metal fasteners
with oxidation.
(5) Remove blockages of foreign object debris so
that the holes and clearances between parts can drain.
(6) For bare metal on any surface of the airplane,
apply corrosion prevention primer, refer to the Application of Corrosion
Preventative Compounds.
(a) Apply a polyurethane topcoat paint to the
exterior painted surface. Refer to the manufacturer's procedures.
(7) Install the dry insulation blankets.
(8) Install the equipment and airplane interior
that was removed to do the corrosion inspection.
CPCP - APPLICATION
Corrosion can cause damage to the airplane's structural integrity and if it is
not controlled, the airframe will carry less load than what is necessary for
continued airworthiness.
A CPCP is a system to control the corrosion in the airplane's
primary structure. It is not the function of the CPCP to stop all of the
corrosion conditions, but to control the corrosion to a level that the airplane's
continued airworthiness is not put in risk.Complete the initial CPCP inspection
in conjunction with the first SID inspection.
Control
Prevention and Control Program Application
A. The CPCP gives the information required for each
corrosion inspection. Maintenance personnel must fully know about corrosion
control. The regulatory agency will give approval and monitor the CPCP for each
airplane.
(1) The CPCP procedures apply to all airplanes that
have exceeded the inspection interval for each location on the airplane.
(a) Cessna recommends that the CPCP be done first on
older airplanes and areas that need greater changes to the maintenance
procedures to meet the necessary corrosion prevention and control requirements.
(2) Maintenance programs must include corrosion
prevention and control procedures that limit corrosion to Level 1 or better on all
Principal Structural Elements (PSEs) and other structure specified in the
Baseline Program. If the current maintenance program includes corrosion control
procedures in an inspection area and there is a report to show that corrosion
is always controlled to Level 1 or better, the current inspection program can
be used.
(a) The Baseline Program is not always sufficient
if the airplane is operated in high humidity (severe) environments, has a
corrosive cargo leakage or has had an unsatisfactory maintenance or repair.
When this occurs, make adjustments to the Baseline Program until the corrosion
is controlled to Level 1 or better. Refer to Section 2A-30-01, Corrosion Severity
Maps, to determine the severity of potential corrosion.
(3) The CPCP consists of the corrosion inspection
applied at a specified interval and, at times, a corrosion inspection interval
can be listed in a Service Bulletin. For the CPCP to be applied, remove all
systems, equipment and interior furnishings that prevent sufficient inspection of
the structure. A nondestructive test (NDI) or a visual inspection can be
necessary after some items are removed if there is an indication of hidden
corrosion such as skin deformation, corrosion under splices or corrosion under
fittings. Refer to the Baseline Program.
(4) The corrosion rate can change between different
airplanes. This can be a result of different environments the airplane operates
in, flight missions, payloads, maintenance practices (for example more than one
owner), variation in rate of protective finish or coating wear.
(a) Some airplanes that operate under equivalent
environments and maintenance practices can be able to extend the inspection
intervals if a sufficient number of inspections do not show indications of
corrosion in that area. Refer to the Glossary.
(5) Later design and/or production changes done as
a result of corrosion conditions can delay the start of corrosion. Operators
that have done corrosion-related Service Bulletins or the improved procedures
listed in the Corrosion Program Inspection can use that specified inspection
interval.
Unless the instructions tell you differently, the
requirements given in this document apply to all airplanes.
(6)
Another system has been added to report all Level 2 and Level 3 corrosion conditions
identified during the second and each subsequent CPCP inspection. This
information will be reviewed by Cessna to make sure the Baseline Program is
sufficient and to change it as necessaryCPCP Basic
CORROSION PREVENTION AND CONTROL PROGRAM (CPCP)
1. Introduction
A. As the airplane ages, corrosion occurs more
often, while, at the same time, other types of damage such as fatigue cracks
occur. Corrosion can cause damage to the airplane's structural integrity and if
it is not controlled, the airframe will carry less load than what is necessary
for continued airworthiness.
(1) To help prevent this, we started a Corrosion
Prevention and Control Program (CPCP). A CPCP is a system to control the
corrosion in the airplane's primary structure. It is not the function of the
CPCP to stop all of the corrosion conditions, but to control the corrosion to a
level that the
airplane's continued airworthiness is not put in
risk.
B. Complete the initial CPCP inspection in
conjunction with the first SID inspection.
2. Corrosion Prevention and Control Program
Objective
A. The objective of the CPCP is to help to prevent
or control the corrosion so that it does not cause a risk to the continued
airworthiness of the airplane.
3. Corrosion Prevention and Control Program
Function
A. The function of this document is to give the
minimum procedures necessary to control the corrosion so that the continued
airworthiness is not put in risk. The CPCP consists of a Corrosion Program Inspection
number, the area where the inspection will be done, specified corrosion levels
and the compliance time. The CPCP also includes procedures to let Cessna
Aircraft Company and the regulatory authorities know of the findings and the
data associated with Level 2 and Level 3 corrosion.
This includes the actions that were done to
decrease possible corrosion in the future to Level 1.
B. Maintenance or inspection programs need to
include a good quality CPCP. The level of corrosion identified on the Principal
Structural Elements (PSEs) and other structure listed in the Baseline Program
will help make sure the CPCP provides good corrosion protection.
NOTE: A good quality program is one that will control all
structural corrosion at Level 1 or better.
C. Corrosion Program Levels.
NOTE: In this manual the corrosion inspection tasks are
referred to as the corrosion program inspection.
(1) Level 1 Corrosion.
(a) Corrosion damage occurring between successive
inspection tasks, that is local and can be reworked or blended out with the
allowable limit.
(b) Local corrosion damage that exceeds the
allowable limit but can be attributed to an event not typical of the operator's
usage or other airplanes in the same fleet (e.g., mercury spill).
(c) Operator experience has demonstrated only light
corrosion between each successive corrosion task inspection; the latest
corrosion inspection task results in rework or blend out that exceeds the
allowable limit.
(2) Level 2 Corrosion.
(a) Level 2 corrosion occurs between two successive
corrosion inspection tasks that requires a single rework or blend-out that
exceeds the allowable limit. A finding of Level 2 corrosion requires repair,
reinforcement or complete or partial replacement of the applicable structure.
(3) Level 3 Corrosion.
(a) Level 3 corrosion occurs during the first or
subsequent accomplishments of a corrosion inspection task that the operator
determines to be an urgent airworthiness concern.
4. References
A. This is a list of references for the Corrosion
Prevention and Control Program.
(1) FAA Advisory Circular AC120-CPCP, Development
and Implementation of Corrosion Prevention and Control Program
(2) FAA Advisory Circular AC43-4A, Corrosion
Control for Aircraft
(3) Cessna Illustrated Parts Catalog - part numbers
P692-12.
(4) Cessna Service Manual - part number D2064-1-13.